Schedule Problems

Reading them, that is.

This reporter Down Under seems to think that the CEV contractors will be selected on May 2nd. In fact, that’s the time that proposals are due (the RFP was released on March 1, with a two-month response time). There’s no way in the world that the source selection could occur that quickly. If you look at the program schedule from the Industry Day briefing a week and a half ago, you can see that the award will actually occur in August.